Great Lakes Water Authority – 14 Mile Water Transmission Line

The Great Lakes Water Authority awarded the Ric-Man|Clark Joint Venture the $93-million Phase-II Installation of an 8-mile long, 54-inch diameter freshwater pipeline to provide a transmission main loop to their existing 14 mile system. The project increased redundancy on this branch of the System and provided a fill line to the existing Haggerty Reservoir. Installation […]

Lansing Board of Water and Light – Central Substation

The new Central Substation was built to remove approximately 51 MVA of load from the existing Eckert Substation in anticipation of the retirement of the Eckert generating station in the future. The design included 138 kV six position breaker-and-a-half scheme with three transformer positions and three line terminal positions. The transformers are 138-13.8 kV 18/24/30 […]

Beaumont Health System – Troy Phased Powerhouse Expansion

The Clark team at the Beaumont Health – Troy Campus accomplished the assembly of the new Powerhouse project. This included the installation of three sizeable CAT generators – 1500KW and 2000KW each – facilitated through removable steel roof monitors positioned on the roof structure. The generator exhaust stacks were thoughtfully directed through an eight-story exhaust […]